Dept. of Trans. PROGRESS Serial No. Contract No. 10-113-09-16 07-235504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 39% 57% 07-LA-5-39.5/42.6 Federal Project: NONE Progress payment No. 10 Payment period ending: 04-20-10 BALFOUR BEATTY INFRASTRUCTURE INC 2333 COURAGE DRIVE SUITE C FAIRFIELD CA 94533 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,120,903.64 951,904.55 2.a. Extra Work 38,309.67 14,783.78 b. Adjustment Comp. 3. Materials on Hand 201,547.57 -49,750.50 4. Earned Subject to Retention 5,360,760.88 916,937.83 5. Mobilization 760,000.00 0.00 6. Total Work Completed 5,919,213.31 7. Deductions -10,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 6,110,760.88 916,937.83 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 916,937.83