Dept. of Trans. PROGRESS Serial No. Contract No. 10-147-13-56 07-235504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 49% 64% 07-LA-5-39.5/42.6 Federal Project: NONE Progress payment No. 11 Payment period ending: 05-20-10 BALFOUR BEATTY INFRASTRUCTURE INC 2333 COURAGE DRIVE SUITE C FAIRFIELD CA 94533 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,625,117.66 1,504,214.02 2.a. Extra Work 50,344.61 12,034.94 b. Adjustment Comp. 3. Materials on Hand 105,624.82 -95,922.75 4. Earned Subject to Retention 6,781,087.09 1,420,326.21 5. Mobilization 760,000.00 0.00 6. Total Work Completed 7,435,462.27 7. Deductions -10,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,531,087.09 1,420,326.21 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,420,326.21