Dept. of Trans. PROGRESS Serial No. Contract No. 10-168-12-32 07-235504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 58% 67% 07-LA-5-39.5/42.6 Federal Project: NONE Progress payment No. 12 Payment period ending: 06-20-10 BALFOUR BEATTY INFRASTRUCTURE INC 2333 COURAGE DRIVE SUITE C FAIRFIELD CA 94533 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,976,454.79 1,351,337.13 2.a. Extra Work 50,344.61 0.00 b. Adjustment Comp. 3. Materials on Hand 69,625.86 -35,998.96 4. Earned Subject to Retention 8,096,425.26 1,315,338.17 5. Mobilization 800,000.00 40,000.00 6. Total Work Completed 8,826,799.40 7. Deductions -10,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 8,886,425.26 1,355,338.17 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,355,338.17