Dept. of Trans. PROGRESS Serial No. Contract No. 10-203-16-23 07-235504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 69% 74% 07-LA-5-39.5/42.6 Federal Project: NONE Progress payment No. 13 Payment period ending: 07-20-10 BALFOUR BEATTY INFRASTRUCTURE INC 2333 COURAGE DRIVE SUITE C FAIRFIELD CA 94533 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,598,377.68 1,621,922.89 2.a. Extra Work 70,811.70 20,467.09 b. Adjustment Comp. 3. Materials on Hand 52,928.98 -16,696.88 4. Earned Subject to Retention 9,722,118.36 1,625,693.10 5. Mobilization 800,000.00 0.00 6. Total Work Completed 10,469,189.38 7. Deductions -10,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 10,512,118.36 1,625,693.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,625,693.10