Dept. of Trans. PROGRESS Serial No. Contract No. 10-236-08-24 07-235504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 81% 82% 07-LA-5-39.5/42.6 Federal Project: NONE Progress payment No. 14 Payment period ending: 08-20-10 BALFOUR BEATTY INFRASTRUCTURE INC 2333 COURAGE DRIVE SUITE C FAIRFIELD CA 94533 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,308,721.78 1,710,344.10 2.a. Extra Work 131,967.20 61,155.50 b. Adjustment Comp. 3. Materials on Hand 22,127.28 -30,801.70 4. Earned Subject to Retention 11,462,816.26 1,740,697.90 5. Mobilization 800,000.00 0.00 6. Total Work Completed 12,240,688.98 7. Deductions -10,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 12,252,816.26 1,740,697.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,740,697.90