Dept. of Trans. PROGRESS Serial No. Contract No. 10-298-08-18 07-235504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 94% 07-LA-5-39.5/42.6 Federal Project: NONE Progress payment No. 16 Payment period ending: 10-20-10 BALFOUR BEATTY INFRASTRUCTURE INC 2333 COURAGE DRIVE SUITE C FAIRFIELD CA 94533 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,334,784.85 1,213,740.15 2.a. Extra Work 228,009.92 39,388.66 b. Adjustment Comp. 3. Materials on Hand 0.00 -18,407.36 4. Earned Subject to Retention 13,562,794.77 1,234,721.45 5. Mobilization 800,000.00 0.00 6. Total Work Completed 14,362,794.77 7. Deductions -10,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 14,352,794.77 1,234,721.45 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,234,721.45