Dept. of Trans. PROGRESS Serial No. Contract No. 10-298-08-18 07-235904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 99% 82% 07-LA-5-6.8/18.4 Federal Project: ACNH-X037(142) ACIM-X037(142) Progress payment No. 25 Payment period ending: 10-20-10 POWELL CONSTRUCTORS 8555 BANANA AVENUE FONTANA CA 92335 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,477,778.95 4,950.00 2.a. Extra Work 44,799.47 0.00 b. Adjustment Comp. -18,555.97 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,504,022.45 4,950.00 5. Mobilization 350,000.00 0.00 6. Total Work Completed 3,854,022.45 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,854,022.45 4,950.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,950.00