Dept. of Trans. PROGRESS Serial No. Contract No. 20-323-14-33 07-238304 PROGRESS PAYMENT VOUCHER %complete: %time: 52% 71% Location: Federal Project: 07-LA-110-13.4/23.1 HSIM-110(848) Progress payment No. 009 Payment period ending: 11-20-20 IBARRA GENERAL ENGINEERING INC 4325 TYROLITE ST RIVERSIDE CA 92509 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,435,789.41 333,246.60 2. a. Extra Work 16,500.00 0.00 b. Adustment Comp. 3. Materials on Hand 9.00 -8,491.40 4. Earned Subject to Retention 1,452,298.41 324,755.20 5. Mobilization 332,500.00 0.00 6. Total Work Completed 1,784,789.41 7. Deductions -12,813.43 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,771,984.98 324,755.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 324,755.20