Dept. of Trans. PROGRESS Serial No. Contract No. 13-023-10-31 07-241304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 65% 54% 07-LA-405-24.4/25.8 Federal Project: IM4-530(20E) Progress payment No. 21 Payment period ending: 01-20-13 ORTIZ ENTERPRISES INCORPORATED 6 CUSHING WAY SUITE 200 IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,266,227.97 448,588.25 2.a. Extra Work 882,709.71 50,743.77 b. Adjustment Comp. 3. Materials on Hand 378,691.29 -61,543.05 4. Earned Subject to Retention 10,527,628.97 437,788.97 5. Mobilization 1,600,000.00 0.00 6. Total Work Completed 11,748,937.68 7. Deductions -3,200.00 -3,200.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 12,124,428.97 434,588.97 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 434,588.97