Dept. of Trans. PROGRESS Serial No. Contract No. 06-081-10-50 07-242004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 22% 27% 07-LA-10-5.8/6.7 Federal Project: NONE Progress payment No. 02 Payment period ending: 03-20-06 OLIVAS VALDEZ INC P O BOX 4576 COVINA CA 91723 Escrow No. 02221 Total Estimate This Estimate 1. Contract Itms Without Mobil. 348,925.25 246,221.25 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 53,360.51 53,360.51 4. Earned Subject to Retention 402,285.76 299,581.76 5. Mobilization 71,250.00 33,750.00 6. Total Work Completed 420,175.25 7. Deductions 8. a.Contract Retentions -37,285.08 -27,014.68 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 436,250.68 306,317.08 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 306,317.08