Dept. of Trans. PROGRESS Serial No. Contract No. 07-115-09-56 07-242004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 07-LA-10-5.8/6.7 Federal Project: NONE Progress payment No. 13 Payment period ending: 04-20-07 OLIVAS VALDEZ INC P O BOX 4576 COVINA CA 91723 Escrow No. 02221 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,875,541.25 9,993.00 2.a. Extra Work 25,274.19 0.00 b. Adjustment Comp. 0.00 -4,000.00 3. Materials on Hand 4. Earned Subject to Retention 1,900,815.44 5,993.00 5. Mobilization 75,000.00 0.00 6. Total Work Completed 1,975,815.44 7. Deductions 8. a.Contract Retentions -95,040.77 -299.65 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,880,774.67 5,693.35 10. Reduction Amt to Escrow 11. Payment to Escrow 95,040.00 12. Net Pymt. this Estimate 5,693.35