Dept. of Trans. PROGRESS Serial No. Contract No. 08-269-08-07 07-242704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 89% 100% 07-LA-210-48.9/49.3 Federal Project: NONE Progress payment No. 05 Payment period ending: 09-20-08 L T ENGINEERING 27601 FORBES ROAD NO 54 LAGUNA NIGUEL CA 92677 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 367,656.40 97,880.20 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 367,656.40 97,880.20 5. Mobilization 49,000.00 0.00 6. Total Work Completed 416,656.40 7. Deductions 8. a.Contract Retentions -18,382.82 -4,894.01 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 398,273.58 92,986.19 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 92,986.19