Dept. of Trans. PROGRESS Serial No. Contract No. 08-329-09-54 07-242704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 07-LA-210-48.9/49.3 Federal Project: NONE Progress payment No. 07 Payment period ending: 11-20-08 L T ENGINEERING 27601 FORBES ROAD NO 54 LAGUNA NIGUEL CA 92677 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 386,197.40 800.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 386,197.40 800.00 5. Mobilization 49,000.00 0.00 6. Total Work Completed 435,197.40 7. Deductions 8. a.Contract Retentions -19,309.87 -40.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 415,887.53 760.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 760.00