Dept. of Trans. PROGRESS Serial No. Contract No. 09-112-13-54 07-242704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 95% 73% 07-LA-210-48.9/49.3 Federal Project: NONE Progress payment No. 12 Payment period ending: 04-20-09 L T ENGINEERING 27601 FORBES ROAD NO 54 LAGUNA NIGUEL CA 92677 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 407,011.40 1,600.00 2.a. Extra Work 40,308.88 1,499.49 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 447,320.28 3,099.49 5. Mobilization 49,000.00 0.00 6. Total Work Completed 496,320.28 7. Deductions 8. a.Contract Retentions -22,366.01 -154.97 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 473,954.27 2,944.52 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,944.52