Dept. of Trans. PROGRESS Serial No. Contract No. 06-235-14-52 07-243504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 32% 26% 07-LA-110-24.5/25.5 Federal Project: ACST-S110(10) PHG-S110(10) Progress payment No. 08 Payment period ending: 08-20-06 PETERSON CHASE GENERAL ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE CA 926145706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 558,440.11 376,703.61 2.a. Extra Work 18,138.23 0.00 b. Adjustment Comp. 3. Materials on Hand 80,847.84 9,974.63 4. Earned Subject to Retention 657,426.18 386,678.24 5. Mobilization 237,500.00 50,000.00 6. Total Work Completed 814,078.34 7. Deductions -1,883.47 -396.52 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 893,042.71 436,281.72 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 436,281.72