Dept. of Trans. PROGRESS Serial No. Contract No. 08-053-08-56 07-243704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 28% 49% 07-VEN-126-0.0/34.6 Federal Project: ACST-P126(52) PHG-P126(52) Progress payment No. 03 Payment period ending: 02-20-08 C AND W CONSTRUCTION SPECIALTIES INC 2419 PALMA DRIVE VENTURA CA 93003 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 311,399.65 305,216.46 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 334,654.27 -95,360.81 4. Earned Subject to Retention 646,053.92 209,855.65 5. Mobilization 59,062.80 2,953.14 6. Total Work Completed 370,462.45 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 705,116.72 212,808.79 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 212,808.79