Dept. of Trans. PROGRESS Serial No. Contract No. 06-144-08-10 07-244504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 10% 36% 07-LA-10-2.1/14.1 Federal Project: ACIM-010-1(784) Progress payment No. 07 Payment period ending: 05-20-06 ALL AMERICAN ASPHALT P O BOX 2229 CORONA CA 928782229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 751,689.30 330,321.32 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 0.00 -15,019.69 4. Earned Subject to Retention 751,689.30 315,301.63 5. Mobilization 140,000.00 0.00 6. Total Work Completed 891,689.30 7. Deductions -224.26 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 891,465.04 315,301.63 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 315,301.63