Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 07-200-13-51 07-244504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-10-2.1/14.1 Federal Project: ACIM-010-1(784) Progress payment No. 22 Payment period ending: 06-20-07 ALL AMERICAN ASPHALT P O BOX 2229 CORONA CA 928782229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,007,582.94 52,376.43 2.a. Extra Work 661,010.32 118,104.52 b. Adjustment Comp. -90,625.22 -8,058.05 3. Materials on Hand 4. Earned Subject to Retention 9,577,968.04 162,422.90 5. Mobilization 280,000.00 0.00 6. Total Work Completed 9,857,968.04 7. Deductions -363,600.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 9,494,368.04 162,422.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 162,422.90