Dept. of Trans. PROGRESS Serial No. Contract No. 13-294-14-43 07-245404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 42% 40% 07-LA-10-31.1/32.3 Federal Project: 07-LA-605-20.2/20.2 NHI-X037(154) Progress payment No. 19 Payment period ending: 10-20-13 M C M CONSTRUCTION P. O. BOX 620 NORTH HIGHLANDS, CA 945603001 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,223,295.80 1,783,186.42 2.a. Extra Work 1,784,618.85 0.00 b. Adjustment Comp. 1,615,262.60 0.00 3. Materials on Hand 69,216.64 -344,911.35 4. Earned Subject to Retention 16,692,393.89 1,438,275.07 5. Mobilization 4,370,000.00 0.00 6. Total Work Completed 20,993,177.25 7. Deductions -21,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 21,041,393.89 1,438,275.07 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,438,275.07