Dept. of Trans. PROGRESS Serial No. Contract No. 15-023-14-36 07-245404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 76% 61% 07-LA-10-31.1/32.3 Federal Project: 07-LA-605-20.2/20.2 NHI-X037(154) Progress payment No. 36 Payment period ending: 01-20-15 M C M CONSTRUCTION P. O. BOX 620 NORTH HIGHLANDS, CA 945603001 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 29,376,070.89 708,025.88 2.a. Extra Work 3,842,235.34 -25,063.42 b. Adjustment Comp. 1,706,042.00 5,479.40 3. Materials on Hand 284,951.96 -10,988.37 4. Earned Subject to Retention 35,209,300.19 677,453.49 5. Mobilization 4,600,000.00 0.00 6. Total Work Completed 39,524,348.23 7. Deductions -45,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 39,764,300.19 677,453.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 677,453.49