Dept. of Trans. PROGRESS Serial No. Contract No. 15-083-10-42 07-245404 PROGRESS PAYMENT VOUCHER %complete: %time: 79% 61% Location: Federal Project: 07-LA-10-31.1/32.3 NHI-X037(154) 07-LA-605-20.2/20.2 Progress payment No. 038 Payment period ending: 03-20-15 M C M CONSTRUCTION P. O. BOX 620 NORTH HIGHLANDS, CA 945603001 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 31,183,090.82 767,896.10 2. a. Extra Work 3,907,523.21 0.00 b. Adustment Comp. 1,706,042.00 0.00 3. Materials on Hand 241,342.80 -32,730.25 4. Earned Subject to Retention 37,037,998.83 735,165.85 5. Mobilization 4,600,000.00 0.00 6. Total Work Completed 41,396,656.03 7. Deductions -45,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 41,592,998.83 735,165.85 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 735,165.85