Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 15-218-14-33 07-245404 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 61% Location: Federal Project: 07-LA-10-31.1/32.3 NHI-X037(154) 07-LA-605-20.2/20.2 Progress payment No. 044 Payment period ending: 07-20-15 M C M CONSTRUCTION P. O. BOX 620 NORTH HIGHLANDS, CA 945603001 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 37,057,067.75 0.00 2. a. Extra Work 4,011,608.54 0.00 b. Adustment Comp. 3,114,633.57 0.00 3. Materials on Hand 88,158.01 0.00 4. Earned Subject to Retention 44,271,467.87 0.00 5. Mobilization 4,600,000.00 0.00 6. Total Work Completed 48,783,309.86 7. Deductions -45,000.00 29,800.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 48,826,467.87 29,800.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 29,800.00