Dept. of Trans. FINAL Serial No. Contract No. 17-123-07-59 07-245404 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 07-LA-10-31.1/32.3 NHI-X037(154) 07-LA-605-20.2/20.2 Progress payment No. 057 Payment period ending: 08-19-16 MCM CONSTRUCTION INC PO BOX 620 NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 41,589,228.00 0.00 2. a. Extra Work 5,748,105.98 0.00 b. Adustment Comp. 7,315,151.34 0.00 3. Materials on Hand 4. Earned Subject to Retention 54,652,485.32 0.00 5. Mobilization 4,600,000.00 0.00 6. Total Work Completed 59,252,485.32 7. Deductions -51,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 59,201,485.32 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00