Dept. of Trans. PROGRESS Serial No. Contract No. 14-267-07-58 07-2464E4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 92% 79% 07-LA-5-13.6/18.5 Federal Project: NONE Progress payment No. 24 Payment period ending: 09-20-14 YAKAR GENERAL CONTRACTORS, INC 113 E. ARROW HWY SAN DIMAS, CA 91773 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 615,795.85 3,250.00 2.a. Extra Work 61,686.19 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 677,482.04 3,250.00 5. Mobilization 60,000.00 0.00 6. Total Work Completed 737,482.04 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 737,482.04 3,250.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,250.00