Dept. of Trans. PROGRESS Serial No. Contract No. 10-204-09-05 07-248904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 76% 88% 07-LA-5-16.9/16.9 Federal Project: ACIM-005-3(30) Progress payment No. 04 Payment period ending: 07-20-10 ODONNELL CONSTRUCTION INC 559 W COVINA BOULEVARD SAN DIMAS CA 91773 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,181,095.90 507,745.90 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,181,095.90 507,745.90 5. Mobilization 88,000.00 4,400.00 6. Total Work Completed 1,269,095.90 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,269,095.90 512,145.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 512,145.90