Dept. of Trans. SEMI-FINAL Serial No. Contract No. 06-256-13-59 07-249304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-VEN-33-48.5/58.0 Federal Project: ACST-P033(63) P-P033(63) Progress payment No. 06 Payment period ending: 06-22-06 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,548,956.57 203,932.00 2.a. Extra Work 78,716.03 56,250.34 b. Adjustment Comp. -16,845.72 -16,845.72 3. Materials on Hand 4. Earned Subject to Retention 2,610,826.88 243,336.62 5. Mobilization 250,000.00 0.00 6. Total Work Completed 2,860,826.88 7. Deductions -10,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,850,826.88 243,336.62 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 243,336.62