Dept. of Trans. PROGRESS Serial No. Contract No. 09-295-12-21 07-250104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 84% 75% 07-LA-105-5.7/5.7 Federal Project: NONE Progress payment No. 04 Payment period ending: 10-20-09 SLATER INC P O BOX 759 FONTANA CA 923340759 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 142,782.75 29,423.75 2.a. Extra Work 14,356.47 14,356.47 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 157,139.22 43,780.22 5. Mobilization 10,800.00 0.00 6. Total Work Completed 167,939.22 7. Deductions -4,445.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 163,494.22 43,780.22 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 43,780.22