Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 10-063-14-44 07-250104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-105-5.7/5.7 Federal Project: NONE Progress payment No. 08 Payment period ending: 02-12-10 SLATER INC P O BOX 759 FONTANA CA 923340759 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 172,662.05 5,251.75 2.a. Extra Work 59,860.78 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 232,522.83 5,251.75 5. Mobilization 10,800.00 0.00 6. Total Work Completed 243,322.83 7. Deductions 0.00 4,445.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 243,322.83 9,696.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 9,696.75