Dept. of Trans. PROGRESS Serial No. Contract No. 12-331-14-11 07-250504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 38% 33% 07-LA-605-0.1/R16.6 Federal Project: ACIM-G605(296) Progress payment No. 03 Payment period ending: 11-20-12 MODERN ALLOYS INC 11172 WESTERN AVENUE STANTON CA 90680 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 424,943.98 165,092.72 2.a. Extra Work 18,130.87 17,312.40 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 443,074.85 182,405.12 5. Mobilization 28,545.49 0.00 6. Total Work Completed 471,620.34 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 471,620.34 182,405.12 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 182,405.12