Dept. of Trans. PROGRESS Serial No. Contract No. 12-086-13-40 07-251504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 92% 100% 07-VEN-101-0.0/12.6 Federal Project: NH-Q101(184) Progress payment No. 16 Payment period ending: 03-20-12 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913521489 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,917,753.97 598,177.83 2.a. Extra Work 204,622.79 107,217.31 b. Adjustment Comp. 1,095,410.65 0.00 3. Materials on Hand 4. Earned Subject to Retention 24,217,787.41 705,395.14 5. Mobilization 1,618,484.91 0.00 6. Total Work Completed 25,836,272.32 7. Deductions -35,700.00 -16,800.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 25,800,572.32 688,595.14 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 688,595.14