Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 14-205-08-25 07-251604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-14-32.1/52.6 Federal Project: NH-P014(69) Progress payment No. 12 Payment period ending: 05-09-14 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 28,844,965.55 321,984.01 2.a. Extra Work 229,363.49 17,587.90 b. Adjustment Comp. -431,245.38 -847,374.43 3. Materials on Hand 4. Earned Subject to Retention 28,643,083.66 -507,802.52 5. Mobilization 405,000.00 0.00 6. Total Work Completed 29,048,083.66 7. Deductions -20,000.00 -20,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 29,028,083.66 -527,802.52 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -527,802.52