Dept. of Trans. FINAL Serial No. Contract No. 13-361-09-27 07-251804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-VEN-101-12.6/R37.0 Federal Project: NH-Q101(183) Progress payment No. 21 Payment period ending: 10-22-12 SECURITY PAVING COMPANY INC 13170 TELFAIR AVENUE SYLMAR CA 91353 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 41,786,118.65 0.00 2.a. Extra Work 821,865.66 0.00 b. Adjustment Comp. 3,165,963.01 1,914,419.55 3. Materials on Hand 4. Earned Subject to Retention 45,773,947.32 1,914,419.55 5. Mobilization 2,500,000.00 0.00 6. Total Work Completed 48,273,947.32 7. Deductions -15,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 48,258,947.32 1,914,419.55 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,914,419.55