Dept. of Trans. PROGRESS Serial No. Contract No. 15-264-12-57 07-252004 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 93% Location: Federal Project: 07-LA-405-39.4/48.6 ACIM-4053(5) Progress payment No. 024 Payment period ending: 09-20-15 MYERS AND SONS CONSTRUCTION LP 4600 NORTHGATE BLVD., STE 100 SACRAMENTO, CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 25,605,293.05 261,531.45 2. a. Extra Work 422,828.19 117,056.15 b. Adustment Comp. 300,025.50 0.00 3. Materials on Hand 4. Earned Subject to Retention 26,328,146.74 378,587.60 5. Mobilization 2,607,000.00 0.00 6. Total Work Completed 28,935,146.74 7. Deductions -23,000.00 -8,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 28,912,146.74 370,587.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 370,587.60