Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 13-212-13-57 07-252504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-5-R59.7/R73.7 Federal Project: SARR-IM00(530) A-IM00(530) Progress payment No. 17 Payment period ending: 05-21-13 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 20,200,764.47 7,840.00 2.a. Extra Work 1,565,530.19 165,979.51 b. Adjustment Comp. 1,596,332.93 122,107.80 3. Materials on Hand 4. Earned Subject to Retention 23,362,627.59 295,927.31 5. Mobilization 200,000.00 0.00 6. Total Work Completed 23,562,627.59 7. Deductions -20,000.00 -20,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 23,542,627.59 275,927.31 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 275,927.31