Dept. of Trans. PROGRESS Serial No. Contract No. 11-355-08-46 07-253304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 77% 7% 07-LA-60-23.9/30.5 Federal Project: ACNH-P060(138) Progress payment No. 12 Payment period ending: 12-20-11 CHUMO CONSTRUCTION INC 14425 JOANBRIDGE STREET BALDWIN PARK CA 91706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,358,023.64 215,906.98 2.a. Extra Work 9,668.87 0.00 b. Adjustment Comp. 1,175,197.45 27,111.88 3. Materials on Hand 176,514.11 65,822.25 4. Earned Subject to Retention 14,719,404.07 308,841.11 5. Mobilization 2,000,000.00 0.00 6. Total Work Completed 16,542,889.96 7. Deductions -2,732.75 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 16,716,671.32 308,841.11 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 308,841.11