Dept. of Trans. PROGRESS Serial No. Contract No. 12-263-13-07 07-253504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 65% 85% 07-LA-5-6.8/11.6 Federal Project: HSIM-G005(295) Progress payment No. 08 Payment period ending: 09-20-12 FBD VANGUARD CONSTRUCTION INC 651 ENTERPRISE CT LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,901,145.20 1,422,619.50 2.a. Extra Work 56,068.42 36,406.08 b. Adjustment Comp. 175,000.00 0.00 3. Materials on Hand 39,224.40 -58,536.28 4. Earned Subject to Retention 6,171,438.02 1,400,489.30 5. Mobilization 750,000.00 37,500.00 6. Total Work Completed 6,882,213.62 7. Deductions -9,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 6,912,438.02 1,437,989.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,437,989.30