Dept. of Trans. PROGRESS Serial No. Contract No. 07-082-10-08 07-257304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 0% 4% 07-LA-1-0.2/40.8 Federal Project: ACST-P001(530) P-P001(530) ACIM-105-3(34) Progress payment No. 01 Payment period ending: 03-20-07 MANUEL BROS INC P O BOX 995 GRASS VALLEY CA 95945 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,795.00 11,795.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 11,795.00 11,795.00 5. Mobilization 6. Total Work Completed 11,795.00 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 11,795.00 11,795.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 11,795.00