Dept. of Trans. PROGRESS Serial No. Contract No. 07-082-11-24 07-257604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 1% 21% 07-LA-66-0.4/5.1 Federal Project: NONE Progress payment No. 01 Payment period ending: 03-20-07 GOLDEN STATE UTILITY CO P O BOX 2968 TURLOCK CA 95381 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,132.43 13,132.43 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 13,132.43 13,132.43 5. Mobilization 6. Total Work Completed 13,132.43 7. Deductions -3,283.11 -3,283.11 8. a.Contract Retentions -1,313.24 -1,313.24 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 8,536.08 8,536.08 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 8,536.08