Dept. of Trans. PROGRESS Serial No. Contract No. 07-171-11-22 07-257604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 70% 86% 07-LA-66-0.4/5.1 Federal Project: NONE Progress payment No. 04 Payment period ending: 06-20-07 GOLDEN STATE UTILITY CO P O BOX 2968 TURLOCK CA 95381 Escrow No. 02287 Total Estimate This Estimate 1. Contract Itms Without Mobil. 714,178.87 398,555.81 2.a. Extra Work 17,815.21 17,815.21 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 731,994.08 416,371.02 5. Mobilization 75,000.00 3,750.00 6. Total Work Completed 806,994.08 7. Deductions 8. a.Contract Retentions -36,599.70 -15,181.30 b. Unsatisfactory Prog. 0.00 8,929.56 c. Reduction after 95% Comp. 9. Total pay to Contractor 770,394.38 413,869.28 10. Reduction Amt to Escrow 11. Payment to Escrow 36,590.00 12. Net Pymt. this Estimate 413,869.28