Dept. of Trans. PROGRESS Serial No. Contract No. 13-325-15-28 07-258804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 47% 24% 07-LA-5-53.6/56.3 Federal Project: ACST-X037(162) P-X037(162) Progress payment No. 05 Payment period ending: 11-20-13 WESTCOAST PUBLIC WORK INC 20058 VENTURA BLVD #318 WOODLAND HILLS CA 91364 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 631,827.30 198,243.80 2.a. Extra Work 40,372.79 34,163.39 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 672,200.09 232,407.19 5. Mobilization 8,225.00 411.25 6. Total Work Completed 680,425.09 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 680,425.09 232,818.44 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 232,818.44