Dept. of Trans. PROGRESS Serial No. Contract No. 15-261-12-01 07-258934 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 100% Location: Federal Project: 07-LA-210-R15.0/R36.0 ACIM-210-1(812) Progress payment No. 032 Payment period ending: 09-20-15 POWELL CONSTRUCTORS INC 8555 BANANA AVENUE FONTANA CA 92335 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,684,568.20 23,300.00 2. a. Extra Work 365,950.38 3,300.00 b. Adustment Comp. 42,148.76 -16,512.46 3. Materials on Hand 4. Earned Subject to Retention 8,092,667.34 10,087.54 5. Mobilization 750,000.00 0.00 6. Total Work Completed 8,842,667.34 7. Deductions -1,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 8,841,667.34 10,087.54 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,087.54