Dept. of Trans. PROGRESS Serial No. Contract No. 13-164-13-34 07-259104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 40% 23% 07-LA-90-1.0/3.5 Federal Project: STP-P090(14) Progress payment No. 05 Payment period ending: 06-20-13 POWELL CONSTRUCTORS INC 8555 BANANA AVENUE FONTANA CA 92335 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 560,617.55 91,763.90 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 560,617.55 91,763.90 5. Mobilization 142,500.00 0.00 6. Total Work Completed 703,117.55 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 703,117.55 91,763.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 91,763.90