Dept. of Trans. PROGRESS Serial No. Contract No. 09-356-15-13 07-259904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 23% 34% 07-LA-710-16.1/18.4 Federal Project: NONE Progress payment No. 09 Payment period ending: 12-20-09 SULLY MILLER CONTRACTING COMPANY 1100 E ORANGETHORPE SUITE 200 ANAHEIM CA 92801 Escrow No. 02404 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,611,036.24 1,070,029.63 2.a. Extra Work 3,512.25 0.00 b. Adjustment Comp. -41,148.63 0.00 3. Materials on Hand 62,685.80 -28,436.70 4. Earned Subject to Retention 5,636,085.66 1,041,592.93 5. Mobilization 1,282,500.00 0.00 6. Total Work Completed 6,855,899.86 7. Deductions 8. a.Contract Retentions -563,608.57 -104,159.30 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 6,354,977.09 937,433.63 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 937,433.63