Dept. of Trans. PROGRESS Serial No. Contract No. 10-026-10-41 07-259904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 26% 37% 07-LA-710-16.1/18.4 Federal Project: NONE Progress payment No. 10 Payment period ending: 01-20-10 SULLY MILLER CONTRACTING COMPANY 1100 E ORANGETHORPE SUITE 200 ANAHEIM CA 92801 Escrow No. 02404 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,368,662.16 757,625.92 2.a. Extra Work 3,912.25 400.00 b. Adjustment Comp. -41,148.63 0.00 3. Materials on Hand 0.00 -62,685.80 4. Earned Subject to Retention 6,331,425.78 695,340.12 5. Mobilization 1,624,500.00 342,000.00 6. Total Work Completed 7,955,925.78 7. Deductions 8. a.Contract Retentions -571,638.89 -8,030.32 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,384,286.89 1,029,309.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,029,309.80