Dept. of Trans. PROGRESS Serial No. Contract No. 10-056-10-32 07-259904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 31% 40% 07-LA-710-16.1/18.4 Federal Project: NONE Progress payment No. 11 Payment period ending: 02-20-10 SULLY MILLER CONTRACTING COMPANY 1100 E ORANGETHORPE SUITE 200 ANAHEIM CA 92801 Escrow No. 02404 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,814,636.74 1,445,974.58 2.a. Extra Work 3,912.25 0.00 b. Adjustment Comp. -41,148.63 0.00 3. Materials on Hand 4. Earned Subject to Retention 7,777,400.36 1,445,974.58 5. Mobilization 1,624,500.00 0.00 6. Total Work Completed 9,401,900.36 7. Deductions 8. a.Contract Retentions -571,638.89 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 8,830,261.47 1,445,974.58 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,445,974.58