Dept. of Trans. PROGRESS Serial No. Contract No. 10-145-12-39 07-259904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 49% 50% 07-LA-710-16.1/18.4 Federal Project: NONE Progress payment No. 14 Payment period ending: 05-20-10 SULLY MILLER CONTRACTING COMPANY 1100 E ORANGETHORPE SUITE 200 ANAHEIM CA 92801 Escrow No. 02404 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,400,395.79 1,145,678.45 2.a. Extra Work 3,912.25 0.00 b. Adjustment Comp. -24,041.13 0.00 3. Materials on Hand 83,779.51 83,779.51 4. Earned Subject to Retention 13,464,046.42 1,229,457.96 5. Mobilization 1,624,500.00 0.00 6. Total Work Completed 15,004,766.91 7. Deductions 8. a.Contract Retentions -673,202.32 -61,472.90 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 14,415,344.10 1,167,985.06 10. Reduction Amt to Escrow 11. Payment to Escrow 673,200.00 12. Net Pymt. this Estimate 1,167,985.06