Dept. of Trans. PROGRESS Serial No. Contract No. 10-168-10-40 07-259904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 53% 54% 07-LA-710-16.1/18.4 Federal Project: NONE Progress payment No. 15 Payment period ending: 06-20-10 SULLY MILLER CONTRACTING COMPANY 1100 E ORANGETHORPE SUITE 200 ANAHEIM CA 92801 Escrow No. 02404 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,577,593.10 1,177,197.31 2.a. Extra Work 3,912.25 0.00 b. Adjustment Comp. -54,128.61 -30,087.48 3. Materials on Hand 0.00 -83,779.51 4. Earned Subject to Retention 14,527,376.74 1,063,330.32 5. Mobilization 1,624,500.00 0.00 6. Total Work Completed 16,151,876.74 7. Deductions 8. a.Contract Retentions -726,368.84 -53,166.52 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 15,425,507.90 1,010,163.80 10. Reduction Amt to Escrow 11. Payment to Escrow 726,360.00 12. Net Pymt. this Estimate 1,010,163.80