Dept. of Trans. PROGRESS Serial No. Contract No. 10-204-10-11 07-259904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 58% 58% 07-LA-710-16.1/18.4 Federal Project: NONE Progress payment No. 16 Payment period ending: 07-20-10 SULLY MILLER CONTRACTING COMPANY 1100 E ORANGETHORPE SUITE 200 ANAHEIM CA 92801 Escrow No. 02404 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,871,228.55 1,293,635.45 2.a. Extra Work 236,805.19 232,892.94 b. Adjustment Comp. -54,128.61 0.00 3. Materials on Hand 67,856.65 67,856.65 4. Earned Subject to Retention 16,121,761.78 1,594,385.04 5. Mobilization 1,710,000.00 85,500.00 6. Total Work Completed 17,763,905.13 7. Deductions 8. a.Contract Retentions -806,088.09 -79,719.25 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 17,025,673.69 1,600,165.79 10. Reduction Amt to Escrow 11. Payment to Escrow 806,080.00 12. Net Pymt. this Estimate 1,600,165.79