Dept. of Trans. PROGRESS Serial No. Contract No. 10-236-09-08 07-259904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 65% 62% 07-LA-710-16.1/18.4 Federal Project: NONE Progress payment No. 17 Payment period ending: 08-20-10 SULLY MILLER CONTRACTING COMPANY 135 S. STATE COLLEGE BL STE40 BREA, CA 92821 Escrow No. 02404 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,267,165.04 2,395,936.49 2.a. Extra Work 243,650.99 6,845.80 b. Adjustment Comp. -54,128.61 0.00 3. Materials on Hand 50,549.82 -17,306.83 4. Earned Subject to Retention 18,507,237.24 2,385,475.46 5. Mobilization 1,710,000.00 0.00 6. Total Work Completed 20,166,687.42 7. Deductions -150,000.00 -150,000.00 8. a.Contract Retentions -925,361.86 -119,273.77 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 19,141,875.38 2,116,201.69 10. Reduction Amt to Escrow 11. Payment to Escrow 925,360.00 12. Net Pymt. this Estimate 2,116,201.69