Dept. of Trans. PROGRESS Serial No. Contract No. 12-235-14-41 07-260104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 83% 100% 07-LA-91-11.7/12.0 Federal Project: NHPP-911(33E) Progress payment No. 08 Payment period ending: 08-20-12 WESTERN STRUCTURES 6005 TYLER STREET RIVERSIDE CA 92503 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,416,510.98 209,403.89 2.a. Extra Work 22,809.12 0.00 b. Adjustment Comp. -427.80 -427.80 3. Materials on Hand 4. Earned Subject to Retention 1,438,892.30 208,976.09 5. Mobilization 125,000.00 0.00 6. Total Work Completed 1,563,892.30 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,553,892.30 198,976.09 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 198,976.09